the work breakdown structure is the same thing as the project organization chart or structure. group of answer choices true false

Answers

Answer 1

The given statement" the work breakdown structure is the same thing as the project organization chart or structure" is False because The work breakdown structure (WBS) and the project organization chart or structure are not the same thing.

The WBS is a project management tool used to define and group a project's deliverables and tasks into smaller, more manageable components.

On the other hand, the project organization chart or structure is a visual representation of the roles and relationships between the individuals or teams working on the project. Therefore, the statement that the work breakdown structure is the same thing as the project organization chart or structure is false.

The WBS is typically a hierarchical structure with various levels of detail, starting with the highest-level components that represent the main deliverables of the project.

For example, the highest level may consist of four main deliverables, each of which is then broken down into smaller, more manageable tasks. The purpose of the WBS is to ensure that all of the tasks and components necessary to complete the project have been identified and that no task is overlooked.


On the other hand, the project organization chart or structure is a visual representation of the people, roles, and teams involved in the project. It typically shows the roles and responsibilities of each person or team, as well as their relationship to the other members of the project team.

It can also be used to identify who is responsible for each task or deliverable. The purpose of the project organization chart or structure is to ensure that everyone is aware of who is responsible for each task, as well as to create an efficient workflow and ensure that everyone is working together towards the same goal.


In conclusion, the work breakdown structure and the project organization chart or structure are not the same thing. The WBS is a tool used to define and group a project's deliverables and tasks into smaller, more manageable components.

The project organization chart or structure is a visual representation of the people, roles, and teams involved in the project. Therefore, the statement that the work breakdown structure is the same thing as the project organization chart or structure is false.

To learn more about work breakdown structure here:

https://brainly.com/question/3757134#

#SPJ11


Related Questions

the primary question the entrepreneur is trying to answer with market research regarding their idea is what?

Answers

The primary question an entrepreneur is trying to answer with market research regarding their idea is what is the demand for the product or service?

Economic Questions: What, How, For Whom?

In order to meet the needs of its people, every society must answer three basic economic questions:

What should we produce?How should we produce it?For whom should we produce it?

A society (or country) might decide to produce candy or cars, computers or combat boots. The goods might be produced by unskilled workers in privately owned factories or by technical experts in government-funded laboratories.

Once they are made, the goods might be given out for free to the poor or sold at high prices that only the rich can afford. The possibilities are endless.

Although every society answers the three basic economic questions differently, in doing so, each confronts the same fundamental problems: resource allocation and scarcity.

Learn more about economic question at https://brainly.com/question/28321604

#SPJ11

if a firm sets a goal of gaining 10 percent more than it put into the business initially, it is most likely using what pricing approach?

Answers

This firm is most likely using a mark-up pricing approach, a strategy that sets a target to make a profit of a certain percentage more than the cost of the good or service. In this case, the firm is aiming to make 10% more than it initially put into the business, which is indicative of a mark-up pricing approach.


Mark-up pricing is typically used when the supplier has relatively limited market power and is unable to set a higher price, or the demand is expected to be low and the supplier needs to incentivize the sale of the good or service. With mark-up pricing, a base price is established and then increased by a fixed percentage. This percentage is usually established by assessing the costs associated with creating and delivering the product or service, plus an additional percentage for profit.

In addition to mark-up pricing, firms may also employ penetration pricing, cost-plus pricing, and premium pricing, depending on their pricing objectives. Penetration pricing is used when the goal is to quickly capture market share by setting a low price and making the product widely available. Cost-plus pricing is used when the goal is to cover costs and make a reasonable profit. Finally, premium pricing is used when the goal is to emphasize a product's quality or when there is an inelastic demand.


In conclusion, when a firm sets a goal of gaining 10 percent more than it put into the business initially, it is most likely using a mark-up pricing approach. Mark-up pricing sets a target to make a profit of a certain percentage more than the cost of the good or service. It is usually used when the supplier has limited market power and is unable to set a higher price. In addition to mark-up pricing, firms may also use penetration pricing, cost-plus pricing, and premium pricing.

For more such questions on Pricing approach.

https://brainly.com/question/30159260#

#SPJ11

Answer:  target return-on-investment

Explanation:

a travel company launches a new app that makes the process of booking your next vacation into a game. this is best categorized as using social media to

Answers

This travel company is utilizing social media in a creative way to market their new app. By turning the process of booking a vacation into a game, they are leveraging the power of social media to attract and engage their target customers.

This type of marketing is known as gamification, which is the use of game elements in non-gaming contexts to engage users and encourage desired behaviors. Gamification often utilizes rewards, points, levels, and leaderboards to encourage users to participate and continue engaging. By turning the process of booking a vacation into a game, the travel company is able to increase user engagement and motivate them to complete the booking process.

for more such questions on vacation.

https://brainly.com/question/29310963

#SPJ11

you are going to receive $5,000 at the end of each year for four years. if the annual discount rate is 7%, what is the present value of this income stream?

Answers

The present value of this income stream is $16,119.27.

This is calculated by taking the amount of $5,000 received at the end of each year and discounting it back to the present day, taking into consideration the 7% annual discount rate.

For example, if we assume the payments are received at the end of each year, then the present value calculation would look like this:

Year 1: 5,000 / (1 + 0.07)^1 = 4,673.03
Year 2: 5,000 / (1 + 0.07)^2 = 4,367.36
Year 3: 5,000 / (1 + 0.07)^3 = 4,081.97
Year 4: 5,000 / (1 + 0.07)^4 = 3,814.82

The total present value of this income stream is then calculated as follows:

4,673.03 + 4,367.36 + 4,081.97 + 3,814.82 = $16,119.27

To know more about present value, click on the link below:

https://brainly.com/question/29586738#

#SPJ11

true or false: the robinson-patman act limits your ability to offer discounts to the chain supermarkets while leaving the price high for the smaller stores.

Answers

True. The Robinson-Patman Act prohibits certain types of price discrimination by prohibiting sellers from offering different prices to different purchasers of commodities of like grade and quality, if the difference in price tends to lessen competition or create a monopoly.

The Robinson-Patman Act is a U.S. federal law that was enacted in 1936 to prevent unfair price discrimination in the sale of goods to different customers. The Act is also known as the Anti-Price Discrimination Act, and it applies to companies engaged in interstate commerce.

The Act prohibits sellers from offering different prices or discounts to different customers for the same product, unless the price difference can be justified by differences in the cost of manufacture, sale, or delivery of the product.

The Act also prohibits sellers from providing services or facilities to one customer that are not offered to all customers on the same terms.

This means that sellers cannot offer lower prices to large chain supermarkets while maintaining higher prices for smaller stores.

To know more about Robinson-Patman Act, click on the link below:

https://brainly.com/question/29237425#

#SPJ11

mark is a broker who signed a listing agreement with a seller to sell their single-family home. a broker associate working under mark brings a buyer to the seller and both parties sign the sales contract. has mark violated any agency laws? no. a dual agency relationship is permitted for residential properties.

Answers

No, Mark has not violated any agency laws in this situation. The scenario described suggests that Mark acted as a listing broker for the seller and that the broker associate working under him brought a buyer to the seller.

Assuming that both parties signed the sales contract and all relevant disclosures and agreements were made, it would be considered a dual-agency relationship. In a dual agency relationship, the same brokerage firm or broker represents both the buyer and the seller in a real estate transaction.

While dual agency relationships are generally permitted for residential properties in some states and countries, it is important that all parties involved are aware of the relationship and that the broker provides full disclosure of any potential conflicts of interest. It is also recommended that both the buyer and the seller obtain independent legal advice before entering into a dual-agency relationship.

To know more about agency laws" .here

https://brainly.com/question/15733071

#SPJ4

for ordinary workers to affect the industrial order, they had to develop their own kind of integrated system. workers' systematic approach to industrialization was

Answers

Workers organized themselves to gain power and autonomy in the industrial order, by forming unions, cooperatives, and associations to bargain for better conditions.

The workers' systematic approach to industrialization was to create an organized structure that allowed them to have more control over the industrial order.

This involved creating associations of workers, cooperatives, unions, and other organizations that had the purpose of collectively bargaining for better working conditions and wages. These organizations would then negotiate with employers, allowing workers to gain more power and autonomy within the industrial order.

Learn more about job: https://brainly.com/question/26355886

#SPJ11

The internal rate of return is the discount rate that equates the present value of the project's free cash flows with the project's initial cash outlay.TrueFalse

Answers

"The statement "The internal rate of return is the discount rate that equates the present value of the project's free cash flows with the project's initial cash outlay" is TRUE.

The internal rate of return (IRR) is a popular financial metric that is used to determine the profitability of an investment. It is the discount rate that makes the net present value (NPV) of a series of cash flows equal to zero. In other words, the internal rate of return is the rate at which the present value of the project's future cash inflows equals the initial investment or cash outlay. The formula for calculating the internal rate of return (IRR) is as follows:

NPV = C₀ + C₁ / (1 + IRR)¹ + C₂ / (1 + IRR)² + ... + Cn / (1 + IRR)n Where: NPV = Net present value C₀ = Initial cash outlay C₁, C₂, ..., Cn = Cash inflows in each period IRR = Internal rate of return Thus, the statement "The internal rate of return is the discount rate that equates the present value of the project's free cash flows with the project's initial cash outlay" is TRUE.

To know more about The internal rate of return (IRR), refers here:

https://brainly.com/question/29581665

#SPJ11

the concentration of effort in a given field of endeavor is called. group of answer choices simplification concentration standardization all the above none of the above

Answers

The concentration of effort in a given field of endeavor is called "concentration" (option b).

Concentration refers to the act of focusing one's attention or mental effort on a particular item. In general, the more effort that is put into concentrating, the more focused the individual becomes, allowing them to ignore distractions, better understand the topic at hand, and create effective solutions.

Maintaining concentration might be challenging, particularly for individuals who are easily distracted. To improve your concentration, you may take the following steps:

1. Prioritize your work: When you have a lot of work to do, it's difficult to concentrate on any one job. Begin by prioritizing your work, setting targets for each, and focusing on one task at a time.2. Eliminate distractions: Turn off the television, radio, or other distractions while you're working on a particular task.3. Take breaks: When you're working on a particularly difficult task, it's essential to take regular breaks to give your mind a rest.4. Exercise: Exercise releases endorphins, which can help you stay focused and alert while also increasing your energy levels.5. Relax: Practicing deep breathing, yoga, or other relaxation techniques might help you relax and focus more effectively when you're working.

So, concentration of effort in a given field of endeavor is called concentration (option b).

Learn more about concentration here: https://brainly.com/question/17206790

#SPJ11

A student is graduating from college in 18 months but will need a loan in the amount of $6,720 for the last three semesters. The student may receive either an unsubsidized Stafford Loan or a PLUS Loan. The terms of each loan are:

Unsubsidized Stafford Loan: annual interest rate of 3.99%, compounded monthly, and a grace period of six months from time of graduation.

PLUS loan: annual interest rate of 4.99%, compounded monthly, with a balance of $7,241.17 at graduation

Which loan will have a higher balance and by how much at the time of repayment?

The Stafford loan will have a higher balance by $107.41 at the time of repayment.
The PLUS loan will have a higher balance by $107.41 at the time of repayment.
The Stafford loan will have a higher balance by $36.53 at the time of repayment.
The PLUS loan will have a higher balance by $36.53 at the time of repayment.

Answers

Answer: To determine which loan will have a higher balance at the time of repayment, we need to calculate the total amount owed for each loan.

For the Unsubsidized Stafford Loan, the total amount owed can be calculated as follows:

Loan amount = $6,720

Annual interest rate = 3.99%

Monthly interest rate = 3.99% / 12 = 0.3325%

Number of months until repayment = 18 + 6 = 24

Total interest = $6,720 x 0.003325 x 24 = $531.84

Total amount owed = $6,720 + $531.84 = $7,251.84

For the PLUS Loan, the total amount owed can be calculated as follows:

Loan amount = $7,241.17

Annual interest rate = 4.99%

Monthly interest rate = 4.99% / 12 = 0.4158%

Number of months until repayment = 18

Total interest = $7,241.17 x 0.004158 x 18 = $553.76

Total amount owed = $7,241.17 + $553.76 = $7,794.93

Therefore, the PLUS loan will have a higher balance at the time of repayment by $543.09 ($7,794.93 - $7,251.84). The correct answer is that the PLUS loan will have a higher balance by $543.09 at the time of repayment.

Explanation:

The PLUS loan will have a higher balance at the time of repayment by $543.94 ($8,189.02 - $7,645.08), so the correct answer is (B) The PLUS loan will have a higher balance by $107.41 at the time of repayment.

What is loan?

A loan is a financial agreement in which one party borrows money from another party with the agreement to pay it back over time, usually with interest. Loans are often used to finance large purchases or investments that would be difficult to pay for all at once.

To determine which loan will have a higher balance at the time of repayment, we need to calculate the future value of each loan. Since the repayment period for both loans is the same, we can compare them directly.

For the unsubsidized Stafford Loan, the present value is $6,720, the annual interest rate is 3.99%, compounded monthly, and the time period is 24 months (18 months until graduation plus 6 months grace period).

Using the future value formula, FV = PV x (1 + r/n)^(nt), where r is the annual interest rate, n is the number of times interest is compounded per year, and t is the time period in years, we get:

FV = $6,720 x (1 + 0.0399/12)^(12*2) = $7,645.08

For the PLUS Loan, the present value is $7,241.17, the annual interest rate is 4.99%, compounded monthly, and the time period is 24 months. Using the same formula, we get:

FV = $7,241.17 x (1 + 0.0499/12)^(12*2) = $8,189.02

Therefore, the PLUS loan will have a higher balance at the time of repayment by $543.94 ($8,189.02 - $7,645.08), so the correct answer is (B) The PLUS loan will have a higher balance by $107.41 at the time of repayment.

Learn more about loan here:

https://brainly.com/question/30104409

#SPJ2

which of the following is a component of pepsi-cola's general environment and may influence how it does business? question 9 options: coca-cola environmental laws inflation two of the above none of the above

Answers

A component of Pepsi-Cola's specific environment which will directly influence how it does business is Coca-Cola. Therefore, the correct option is A.

The specific environment comprises of the external factors and have an immediate and direct effect on the organization's success. As a result, these elements have a direct impact on the company's performance. These forces are specific to a particular organisation or a company. In other words, the specific environment of an organization consists of the particular industry, suppliers, clients, competitors, new entrants, and other stakeholders that have a direct impact on its achievement.

Hence, as Coca-Cola is a direct competitor and thus a component of Pepsi's specific environment. It will directly affect the company's success which is beyond the company's control. Therefore, the correct option is A.

Note: The question is incomplete. The complete question probably is: Which of the following is a component of Pepsi-Cola's specific environment and will directly influence how it does business? a. Coca-Cola b. laws concerning sanitation c. inflation d. the increased popularity of energy drinks e. the development of vending machines that accept debit cards.

Learn more about External factors:

https://brainly.com/question/1284168

#SPJ11

data was collected on a particular stock every month for a period of 12 months. this is an example of

Answers

The given data collected on a particular stock every month for a period of 12 months is an example of time-series data.

What is time-series Data?

Time-series data refers to the set of statistical observations in which each data point is associated with a unique timestamp or interval. Time-series data is essential in a variety of fields, including economics, finance, weather forecasting, engineering, and scientific research. Some of the typical examples of time-series data are:

Monthly or Quarterly Financial reports, Hourly Temperatures Daily Traffic statistics, Minute-level stock prices, Monthly Website Traffic Quarterly Sales reports ,Yearly Climate changes And so on. Time-series data is used to make informed decisions about future trends, forecasts, and patterns based on historical observations. In order to capture the seasonality or other patterns in the data, time-series data is usually plotted on a graph over time.

To know more time-series refer to:

https://brainly.com/question/28151084

#SPJ11

how can managers identify the ethically questionable applicants even before they become part of the workforce?

Answers

Give the person a chance to defend their acts or change their conduct first. If a straightforward discussion doesn't fix the problem, you might need to contact your boss, HR, or a workplace ethics hotline.

How can managers spot candidates who have ethical concerns before they join the workforce?

Ask potential hires to respond to a series of questions about their ethical principles and thought processes as part of an ethics exam. This can provide you a more comprehensive understanding of a candidate's ethical inclinations when done in tandem with reference checks. being truthful in an advertisement, preserving discretion throughout the selection process, ensuring that all candidates are subjected to the same interview questions, and requesting that they declare if any members of their immediate family or close friends are employed by the same company.

Honesty, fairness, and equity in interpersonal, professional, and academic interactions as well as in research and scholarly pursuits are characteristics of ethical behavior. The rights, variety, and dignity of both individuals and groups of people are respected in ethical behavior.

Learn more about workforce:

https://brainly.com/question/28843491

#SPJ1

anton is very particular about the clothes he buys. he doesn't like fabric that itches his skin, and he has a hard time getting clothes to fit him. what benefit would shopping in a store give anton over other retail channels?

Answers

Anton would benefit from shopping in a store because it would give him the opportunity to touch and try on the clothes before purchasing them.

Shopping in a store also provides the benefit of being able to receive personal assistance from store employees. Anton can ask for help finding clothes that meet his specific needs and can receive advice on the best fit and fabric for his body type and skin sensitivity. This level of personal assistance can be especially valuable for customers who have difficulty finding clothes that meet their needs through other retail channels.

Learn more about Shopping: brainly.com/question/30238333

#SPJ11

Managers are able to influence which of the following types of external forces? (Check all that apply.)
Multiple select question.
A. currency exchange rates
B. the structure of their industry
C. interest rates
D. strategic group composition

Answers

Managers can influence the following types of external forces:

The correct options are A, B, C and D.

External factors include all the factors that a firm cannot control, but which may affect its success or failure. Managers, on the other hand, have no control over the vast majority of external factors, but they can exert some influence on some of them.

Currency exchange rates: Currency exchange rates can have a big impact on a company's revenue and profit margins, and managers can influence them by creating sound financial policies and strategies that help the company navigate changes in the currency market.

The structure of their industry: The structure of their industry refers to the competitive environment in which a company operates, and managers can influence it by collaborating with other players in the industry to establish industry standards and norms that benefit everyone.

Interest rates: Interest rates are a critical component of a firm's financial strategy, and managers can influence them by developing sound financial policies that minimize the company's exposure to fluctuations in interest rates.

Strategic group composition: A strategic group is a group of firms in an industry that share similar strategies, resources, and goals. Managers can influence strategic group composition by collaborating with other firms to establish industry standards and norms that benefit everyone.

Industry standards and norms can help minimize wasteful competition and promote mutually beneficial cooperation that can improve the industry as a whole.

Therefore all the option are acorrect.

To learn more about exchange rates visit: https://brainly.com/question/10187894

#SPJ11

(T/F) cash revenue generated from notes receivable appears in the operating activities section of the statement of cash flows but as a non-operating item on the income statement.

Answers

The given statement "cash revenue generated from notes receivable appears in the operating activities section of the statement of cash flows but as a non-operating item on the income statement" is True because it is generated from lending activities.

It is divided into three sections: operating activities, investing activities, and financing activities.  Operating activities include transactions that affect the day-to-day business operations, such as cash received from customers or cash paid to suppliers.

Cash revenue from notes receivable, which is money received from borrowers, is classified under operating activities because it is a result of the company's primary business activities. Cash revenue from notes receivable is considered a non-operating item on the income statement because it does not arise from the primary activities of the business.

Instead, it is generated from lending activities, which are considered secondary or incidental to the company's main business. Therefore, cash revenue from notes receivable appears as a non-operating item on the income statement, but it is included in the operating activities section of the statement of cash flows.

Know more about cash revenue here:

https://brainly.com/question/30522754

#SPJ11

true or false: special interest issues provide substantial widespread benefits to citizens while imposing a large individual cost only on the wealthiest citizens.

Answers

The given statement, "special interest issues provide substantial widespread benefits to citizens while imposing a large individual cost only on the wealthiest citizens," is false (F) because special interest issues often only benefit a specific group or industry.

While the cost is often spread out among all citizens or disproportionately affects marginalized communities.

Special interest issues may involve policies or legislation that favor a specific group or industry, such as tax breaks or subsidies. While these policies may provide benefits to those groups, they may also impose costs on other individuals or communities. For example, a tax break for a particular industry may lead to reduced revenue for the government, which may result in cuts to public services or increased taxes on other citizens.

Additionally, marginalized communities may be disproportionately affected by special interest policies, as they may lack the resources or political influence to effectively advocate for their interests. Therefore, while special interest issues may provide benefits to certain groups, they may also impose costs on others and may not necessarily provide substantial widespread benefits to all citizens.

Learn more about Special interest https://brainly.com/question/14363531

#SPJ11

on august 1, 20x1, the accountant for western exports downloaded the company's july 31, 20x1, bank statement from the bank's website. the balance shown on the bank statement was $28,810. the july 31, 20x1, balance in the cash account in the general ledger was $13,687. jenny iglesias, the accountant for western exports, noted the following differences between the bank's records and the company's cash account in the general ledger. an electronic funds transfer for $14,900 from defontaine equipment, a customer located in france, was received by the bank on july 31. check 1422 was correctly written and recorded for $1,200. the bank mistakenly paid the check for $1,230. the accounting records indicate that check 1425 was issued for $69 to make a purchase of supplies. however, examination of the check online showed that the actual amount of the check was for $99. a deposit of $850 made after banking hours on july 31 did not appear on the july 31 bank statement. the following checks were outstanding: check 1429 for $1,254 and check 1430 for $146. an automatic debit of $267 on july 31 from centralcomm for telephone service appeared on the bank statement but had not been recorded in the company's accounting records. required: prepare a bank reconciliation for the firm as of july 31. record general journal entries for the items on the bank reconciliation statement that must be journalized. date the entries july 31, 20x1. analyze: what effect on total expenses occurred as a result of the general journal entries recorded?

Answers

On August 1, 20x1, the accountant for Western Exports downloaded the company's July 31, 20x1, bank statement from the bank's website. The balance shown on the bank statement was $28,810.

The July 31, 20x1, balance in the cash account in the general ledger was $13,687. Jenny Iglesias, the accountant for Western Exports, noted the following differences between the bank's records and the company's cash account in the general ledger.



Bank Reconciliation for Western Exports as of July 31, 20x1:



Additions to the Book Balance:




 Electronic funds transfer from Defontaine Equipment in France for $14,900
 Check 1422 mistakenly paid for $1,230 instead of the intended $1,200
 Check 1425 incorrectly recorded for $69 instead of $99
 Deposit of $850 made after banking hours on July 31



Subtractions from the Book Balance:




 Check 1429 for $1,254
 Check 1430 for $146
 Automatic debit of $267 on July 31 from Centralcomm for telephone service



Adjusted Book Balance: $25,689



General Journal Entries:




 Debit Cash: $14,900

Credit Accounts Receivable: $14,900

 Date: July 31, 20x1

 Debit Cash: $1,230

Credit Accounts Payable: $1,230

 Date: July 31, 20x1
 
 Debit Supplies: $30

Credit Cash: $30

 Date: July 31, 20x1
 
 Debit Cash: $850

Credit Accounts Receivable: $850

 Date: July 31, 20x1
 
 Debit Accounts Payable: $1,254

Credit Cash: $1,254

 Date: July 31, 20x1
 
 Debit Accounts Payable: $146

Credit Cash: $146

 Date: July 31, 20x1
 
 Debit Accounts Payable: $267

Credit Cash: $267

 Date: July 31, 20x1



Analysis: The total expenses for the month of July increased as a result of the general journal entries recorded for the bank reconciliation. This is because several payments were incorrectly recorded or paid by the bank, leading to increased expenses for the month.

To learn more about bank reconciliation, refer below:

https://brainly.com/question/29097188

#SPJ11

the advantage of using command and control to solve an externality problem is that: it is inflexible, and some problems require an inflexible approach. it is a very flexible approach. it solves the problem efficiently without the government requiring very much information. it is usually the least costly approach.

Answers

The advantage of using command and control to solve an externality problem is that it is usually the least costly approach.

This means that by implementing strict regulations and enforcing them, the government can directly address the issue without needing to gather extensive information or use a more flexible approach, which might not be as effective in solving the problem.

Command and control regulation refers to government regulations that require specific actions or prohibit specific behaviours in order to address an externality problem. While this approach can be effective in addressing the problem, it can also be inflexible and may not allow for innovation or adaptation to changing circumstances.

Additionally, command and control regulation may require significant resources for monitoring and enforcement, which can be costly for both the government and the regulated entities. In contrast, other approaches, such as market-based mechanisms like taxes or cap-and-trade systems, can provide incentives for reducing the externality while minimizing the need for costly regulation.

For more such questions on command and control

https://brainly.com/question/14696636

#SPJ11

in 2014, the top 10 percent of u.s. households received approximately of all income. a. 25 b. 70 c. 50 d. 10

Answers

In 2014, the top 10 percent of u.s. households received approximately 25% of all income.  (A)

In 2014, the top 10% of US households received approximately 25% of all income. This is significantly higher than the median of the bottom 90%, which was only 14.6%.

This means that the top 10% earned roughly 10 times more than the bottom 90%. The gap between the rich and the poor has been steadily increasing since the early 1980s and this trend has continued through 2014.

The disparity between the top 10% and the rest of the population is indicative of economic inequality in the US. This has far reaching consequences on economic growth, social mobility, and opportunity.

To know more about economic inequality click on below link:

https://brainly.com/question/30239024#

#SPJ11

revisit the costs for the khalid company below. what is the product's contribution margin ratio? group of answer choices 46.6% 58.3% 30.0% 52.3% none of the above

Answers

The product's contribution margin ratio is 50%.The option E. None of the above is correct.

About contribution margin ratio

The contribution margin ratio for the product can be calculated using the following formula:

Contribution margin ratio = (Contribution margin / Sales) x 100

Where contribution margin is calculated as:

Contribution margin = Sales - Variable Expenses Given below is the data for Khalid Company:

Sales = $150,000

Variable expenses = $75,000

Fixed expenses = $50,000

Using the above data, we can calculate the contribution margin as:

Contribution margin = Sales - Variable expenses= $150,000 - $75,000= $75,000

And the contribution margin ratio as:

Contribution margin ratio = (Contribution margin / Sales) x 100= ($75,000 / $150,000) x 100= 50%

Therefore, the product's contribution margin ratio is 50%.(Option E. None of the above)

Learn more about margin ratio at

https://brainly.com/question/29534784

#SPJ11

which of the following is the best illustration of the tragedy of the commons? responses depletion of fishing stocks in the north atlantic depletion of fishing stocks in the north atlantic collective farming of wine grapes in communities in france collective farming of wine grapes in communities in france using national forests for wood production and harvesting using national forests for wood production and harvesting allocation of all nuclear wastes to one site in nevada allocation of all nuclear wastes to one site in nevada agreements among western ranchers to jointly manage common grazing land

Answers

The best illustration of tragedy of the commons among options provided is the depletion of fishing stocks in the North Atlantic.

What is a tragedy?

Tragedy is a genre of drama that portrays the downfall of a character or characters, usually as a result of their own flaws or errors in judgment. It often features intense emotions, conflict, and suffering, and aims to evoke feelings of pity, fear, and catharsis in the audience. Tragic characters are typically of high status or importance, and their tragic flaw or mistake leads to their downfall and often the downfall of those around them. The tragic plot follows a specific structure known as the "tragic arc," which begins with a state of happiness and ends with the tragic hero's demise. Through tragedy, audiences are reminded of the frailty of human existence and the consequences of our actions.

To learn more about conflict, visit:

https://brainly.com/question/858228

#SPJ1

providing support to the community is an example of a(n) responsibility for a small business. a. discretionary b. legal c. ethical d. economic

Answers

Providing support to the community is an example of a(n) ethical responsibility for a small business. The correct answer is option c.

What is meant by small business?

A small business is a privately held organization that typically employs fewer than 500 employees. The vast majority of small businesses have fewer than 20 employees. Small businesses are crucial to the nation's economy since they generate income, employment, and growth. These businesses are often founded by entrepreneurs who seek to make their mark in the business world, provide a valuable service, or fill a niche in the marketplace.

Ethical responsibility is the obligation of a company to be ethical in its dealings with the community and the environment in which it operates. A small business has a moral responsibility to protect the environment, foster equality, provide fair labor conditions, and operate with integrity.

Learn more about small business here: https://brainly.com/question/28522792

#SPJ11

jackson company purchased back 1,000 shares of $2 common stock for $20. jackson then resold the stock for $25. the amount credited to additional paid-in capital from treasury stock is a.$10,000. b.$2,000. c.$5,000. d.$20,000.

Answers

The amount credited to additional paid-in capital from treasury stock is $5,000.The correct option is c.

Jackson Company purchased 1,000 shares of $2 common stock for $20,000. This is an investment of $20,000 in treasury stock. The company then resold the stock for $25,000. The difference of $5,000 is the amount credited to additional paid-in capital from treasury stock.

Treasury stock is the number of shares that a company has issued and then repurchased from the shareholders. A company buys treasury stock either to give its shareholders a return, for its stocks to be publicly traded, or to gain control of the company. Treasury stock can be either retired or held in the company's treasury.

When a company holds back the treasury stock, it's as though the shares were never issued, and the company reduces its total number of outstanding shares accordingly. When a company buys back its shares, the money that the company receives from selling those shares would be added to the additional paid-in capital account.

When it sells those shares again, the proceeds of the sale are removed from the additional paid-in capital account, and the difference is debited to the treasury stock account, which is a reduction in equity in the balance sheet. Therefore, the amount credited to additional paid-in capital from treasury stock is $5,000. So, the correct option is (c) $5,000.

Learn more about common stock and treasury stock here:

brainly.com/question/11324832

#SMJ11

given the original quanity of 75 protocol droids, if the price of power converters increases by 15% calculate the new equilibrium quantity in the protocol droid market

Answers

The new equilibrium quantity in the protocol droid market is 60. Hence, the correct option is (B) 60.

Equilibrium quantity is defined as the quantity of goods in a particular market at which the supply and demand curve meets each other. It means that the price at which the quantity of goods supplied equals the quantity of goods demanded is called equilibrium price. The equilibrium quantity is the quantity demanded and supplied at the equilibrium price.

In other words, it is the quantity of goods for which buyers and sellers agree to a particular price. Now, let's solve the given problem:

Given: The original quantity of 75 protocol droids. The price of power converters increased by 15%.We have to calculate the new equilibrium quantity in the protocol droid market.

Therefore, the new quantity demanded by the buyers will be lower as compared to the original quantity. Let's calculate the new quantity:

Quantity of protocol droids demanded = 75 - 15% of 75= 75 - 11.25= 63.75. Hence, the correct option is (B) 60.

For more about equilibrium quantity:

https://brainly.com/question/31012711

#SPJ11

products consumers purchase frequently and with a minimum of shopping effort are known as group of answer choices shopping products unsought products habitual products convenience products

Answers

Products that are frequently purchased by consumers with a minimum of shopping effort are known as convenience products.

What are convenience products?

Convenience products are products that are frequently purchased by consumers with a minimum of shopping effort. These types of products include products such as chewing gum, toothpaste, beverages, and candy. Convenience products are products that are widely available in most retail stores and can be easily obtained by consumers.

They are usually low-priced products and require little consideration or research by consumers before they are purchased. These types of products are bought by consumers based on the belief that the product is easily accessible, low-priced, and that the consumer already knows the product's quality.

What are the characteristics of convenience products?

Below are some of the characteristics of convenience products:

They are low-priced.They are widely available in most retail stores.They require little consideration or research by consumers before they are purchased.They are bought by consumers based on the belief that the product is easily accessible, low-priced, and that the consumer already knows the product's quality.

The purchase of these products does not involve much deliberation by the consumer before making the purchase. Consumers frequently purchase convenience products because of their low prices and ease of accessibility. They are widely available in most retail stores and are easy to obtain.

To know more about convenience products  refer here :

https://brainly.com/question/29739607#

#SPJ11

emergencies, vacations, social events, and major purchases are examples of short-term needs. a. true b. false

Answers

The given statement "Emergencies, vacations, social events, and major purchases are examples of short-term needs" is true.

Short-term needs are wants or needs that can be met quickly or in the near future. Emergencies, vacations, social events, and major purchases are examples of short-term needs. A short-term need is one that you will pay for in less than a year.

Long-term wants or requirements, such as a house, a child's education, or a comfortable retirement, may take years to save for and obtain.

Emergencies may include unexpected health expenditures, car repairs, or home repairs that need immediate attention.Vacations may be a brief weekend trip to a nearby city or a week-long vacation abroad, all of which are planned ahead of time. Social events may include a special date, an invitation to a dinner or lunch, or a party invitation. Buying a vehicle or upgrading your electronic gadget are examples of major purchases.

The various types of short-term expenses are emergencies, vacations, social events, and major purchases.

To know more about short-term expenses click here:

https://brainly.com/question/30197449

#SPJ11

circumstances that likely will result in an audit opinion that departs from an unqualified opinion include

Answers

Circumstances that likely will result in an audit opinion that departs from an unqualified opinion include:

Material misstatements in the financial statementsMisrepresentations in management's representationsLimitations on the scope of the auditInadequate or insufficient evidenceNon-compliance with laws or regulations

An audit opinion that differs from an unqualified opinion may be issued if the auditor discovers material misstatements or inconsistencies in the financial statements if the auditor is limited in the extent of their audit, or if there is a disagreement between the auditor and the client regarding financial statement presentation or disclosure.

These circumstances indicate that the auditor is unable to express an unqualified opinion on the financial statements.

An auditor must also be able to conduct the audit with sufficient scope to obtain adequate audit evidence. If the auditor is unable to complete an appropriate audit for any reason, such as a limitation on scope, they may be unable to issue an unqualified opinion.

Finally, if the auditor and client disagree on a financial statement presentation or disclosure, the auditor may be unable to express an unqualified opinion.

Learn more about audits here:

https://brainly.com/question/7890421

#SPJ11

which of the following dictates overall business objectives? group of answer choices the broad environment in which the business operates public relations strategies public relations programs marketing and advertising strategies

Answers

The broad environment in which the business operates dictates overall business objectives. This includes factors such as the external economic environment, technological environment, legal and political environment, and social and cultural environment. These environmental factors can help shape the overall business objectives of the organization.

The broad environment in which the business operates dictates overall business objectives. The external environment, which includes factors such as economic conditions, political and legal factors, technological changes, social and cultural factors, and competition, has a significant impact on a business's overall objectives. A business must analyze and understand the external environment to determine the best course of action and establish goals that align with the opportunities and challenges presented by the environment. Public relations strategies and programs, as well as marketing and advertising strategies, may be important components of a business's overall strategy, but they are not the factors that dictate the overall business objectives

Learn more about Business plan: brainly.com/question/25534066

#SPJ11

a) if you invest $3,500 now in return for a guaranteed $7,000 income at a later date, when must you receive your money in order to earn exactly 8% per year by simple interest? b) how long will it take by compounding interest?

Answers

a) It will take 12.5 years for an individual who invests $3,500 now for a guaranteed income of $7,000 later to earn exactly 8% per year by simple interest. b) It will take approximately 8.16 years by compound interest when all other factors remains the same.

a)  The formula for simple interest is given as;

I = Prt

where I represents the interest amount, P represents the principal amount, r represents the interest rate, and t represents the time duration. The interest rate is given as 8% per year, thus r = 8/100 = 0.08. Also, the principal amount is given as $3,500 and final amount is $7,000, Hence the interest earn is $3.500 ($7,000 - $3,500).

Hence,

I = Prt

3,500 = 0.08 × 3,500 × t

t = 3,500/ (0.08 × 3,500)

t = 12.5 years

Thus, it will take approximately 12.5 years by simple interest for the individual to earn $7,000.

b) Compound interest is given as the sum of the principal amount and the compound interest amount. The formula for compound interest is given as;

A = P(1 + r/n)^nt

where A represents the compound interest amount, P represents the principal amount, r represents the interest rate, t represents the time duration, and n represents the number of times interest is compounded per year. It is assumed that the interest is compounded annually, i.e., n = 1.

Also, we have P = 3,500, r = 8/100 = 0.08, and A = 7,000. Thus

A = P(1 + r/n)^nt

7,000 = 3,500(1 + 0.08/1)^t

2 = (1.08)^t

log (1.08) 2 = t × log (1.08)

t = log (1.08) 2/ log (1.08 )≈ 8.16 years

Thus, it will take approximately 8.16 years by compounding interest for the individual to earn $7,000.

Learn more about Compound interest:

https://brainly.com/question/24924853

#SPJ11

Other Questions
Can someone Please help me. Angela is using a game piece with faces labeled A, B, C, and D. What is the sample space for rolling the game piece? Which of the following best describes the expression 7(x + 9)? (1 point) aThe product of a constant factor 7 and a 2-term factor x + 9 bThe sum of a constant factor 7 and a 2-term factor x + 9 cThe sum of constant factors 7 and x + 9 dThe product of constant factors 7 and x + 9 a lawyer is presenting a hair sample with its corresponding nuclear dna that was found at the crime scene. how will this most likely affect the criminal case? The bezant was used in places from England to China. *O TrueO False assume that a species has a diploid chromosome number of 24. the term applied to an individual with 25 chromosomes would be . Does adversity make one stronger? Explain. Support your opinion with at least one example. if we monitor a point on a wire where there is a current for a certain time interval, which gives the chargef that moves through the point in that interval? the number of hours needed to complete a trip, h, varies inversely with the driving speed, s. a trip can be completed in 5 hours at a speed of 60 miles per hour. find the equation that represents this relationship. stephen weighs 185 pounds and is at 17% body fat. he wants to drop down to 10% body fat. how many pounds does he need to lose? Whoever gets this correct gets brainliestSouthern African urban centers are often characterized by:A. little ethnic and racial diversity. B. high levels of income inequality. O C. low rates of crime and unemployment. D. high levels of erlucation and literacy. true or false: as an adult, if you had to choose only one of these two foods (corn or beans) to provide you with essential amino acids, you would choose corn, because it provides more essential amino acids than beans. all hormones are all hormones are proteins. chemical messengers. steroids. cholesterol based. inorganic compounds. Please Help Me I Will Give Out Extra Points And The Crown 2.0Re-read the poem The Red Wheelbarrow by William Carlos Williams and answer the question that follows:so much dependsupona red wheelbarrowglazed with rainwaterbeside the whitechickensWhat is the significance of the red wheelbarrow?Question 2 options:The wheelbarrow's red color makes it easy to find The wheelbarrow is where the chickens play The wheelbarrow collects the rain waterThe wheelbarrow is needed for the farmer to work The company Sea Esta has ten members on its board of directors. In how many different ways can itelect a president, vice-president, secretary and treasurer? what is unusual about the position of uranus and neptune in the nice model of solar system formation? A person travels 30 miles in 40 minutes 4.a main idea, according to the textbook, is that the history of humanity is characterized by a departure from what? which two fields in an ethernet frame help synchronize device communications but are not counted toward the frame's size? on january 1, 2022, wheeler inc purchases a building for $800,000 and places it into service. when wheeler inc records depreciation on the building on december 31, 2022, it will increase depreciation expense and: