a project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

Answers

Answer 1

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project has a 20% chance of being completed before 112 days (rounded to the nearest day).

Let us first calculate the standard deviation, which is the square root of the variance:

Variance = 100

Standard deviation = √variance

                                = √100

                                = 10

Therefore, the standard deviation is 10.

There are a variety of methods for calculating probabilities based on a standard normal distribution, such as using a Z-table or a normal distribution calculator. We can also use the Z-score formula to calculate the number of standard deviations from the mean that a particular value lies in, which we will use to determine the appropriate probability.

In this case, we have the following information:

Mean = 120 days

Standard deviation = 10 days

X = the number of days before the completion of the project

We want to find the value of X that corresponds to a 20 percent chance that the project will be completed by that date. This can be determined by finding the Z-score for the 20th percentile, which is -0.8416 using a Z-table or a normal distribution calculator.

Then we will use the formula

Z = (X - μ) / σ

to solve for X,

where μ is mean and σ is the standard deviation.

-0.8416 = (X - 120) / 10-8.416

            = X - 120-8.416 + 120

           = 111.584

Therefore, there is a 20% chance that the project will be finished before the 112th day (rounded to the nearest day).

Learn more about normal distribution at https://brainly.com/question/4079902

#SPJ11


Related Questions

you have a novel idea. hedge eur 50,000,000 in the forward market and leave the rest unhedged. what will be your revenue if the spot rate in 12 months is usd 1.23/eur?

Answers

Your potential revenue from this novel idea will be USD 11,500,000 if the spot rate in 12 months is USD 1.23/EUR.

To calculate the potential revenue of your novel idea, you need to consider the hedge amount, the spot rate in 12 months, and the total amount unhedged.

The hedge amount of EUR 50,000,000 will not change and is not dependent on the spot rate. However, the total amount unhedged will depend on the spot rate in 12 months.

If the spot rate in 12 months is USD 1.23/EUR, then the unhedged amount will be USD 61,500,000.

To calculate this, take the total amount of EUR 80,000,000 and multiply it by the spot rate of 1.23. This will give you the unhedged amount of USD 61,500,000.

The revenue will be the unhedged amount minus the hedge amount. Therefore, the revenue of your novel idea will be USD 11,500,000 if the spot rate in 12 months is USD 1.23/EUR.

This is calculated by taking the unhedged amount of USD 61,500,000 and subtracting the hedge amount of EUR 50,000,000.

To know more about potential revenue, refer here:

https://brainly.com/question/29034126
#SPJ11

kama bought 20 shares, each costing $750. she decides to resell her shares for $17,250. she pays 16% commission. calculate kama's income after selling her shares.

Answers

Kama's income after selling her shares, taking into account the 16% commission she paid, is $14,490.

To calculate Kama's income, we first need to calculate the total cost of the shares she bought, which is 20 x $750 = $15,000. When she sold her shares, she received $17,250, but she had to pay a commission of 16% of that amount, which is 0.16 x $17,250 = $2,760.

So her income after selling her shares is the difference between the amount she received and the commission she paid, which is $17,250 - $2,760 = $14,490.

Learn more about sell stocks https://brainly.com/question/28540029

#SPJ11

Answer:

-510

Explanation:

a company wants to insure against the risk associated with the non-payment of a foreign receivable. which agency would be the most appropriate?

Answers

The ECAs are a reliable source for companies to mitigate their risk when dealing with foreign buyers.

A company wishing to insure against the risk associated with the non-payment of a foreign receivable would most likely want to look into Export Credit Agencies (ECAs).

ECAs are government-sponsored entities which provide insurance or loans to help companies with the non-payment risk associated with selling to foreign buyers.

This type of insurance is typically backed by the full faith and credit of the government, meaning the government is obligated to pay the insurance claim should the foreign buyer default on their payments.

Furthermore, the policies and coverage offered by ECAs are typically more comprehensive and cost-effective than traditional commercial insurance policies. ECAs are a reliable source for companies to mitigate their risk when dealing with foreign buyers.

To know more about  ECAs refer here:

https://brainly.com/question/8664594#

#SPJ11

piers is using the story line approach in his presentation. he says that the coffee shop chain he works for faces the challenge of improving its customer service orientation. after describing a sandwich chain that is similar to his company in size and target market, he explains the specific approach to training that the sandwich chain implemented in order to improve its customer service. what aspect of a business story does his explanation about the training program represent?

Answers

A business PowerPoint presentation may make excellent use of storytelling, which is a potent tool for communication.

The storylines should tie together when employing a narrative line method for corporate presentations.

Business presentations should connect data with people and their company objectives when adopting a story line approach. The final phase in Antwan's preparation for a business presentation should be to better grasp the requirements of his audience.

Why is a storytelling approach helpful in corporate presentations?

Because people can relate to tales, telling them is a captivating presentation technique. Tales captivate an audience, arouse empathy, build trust, and spur action. You will be more persuasive if you practice your storytelling abilities.

To know more about Business story visit:-

https://brainly.com/question/4523763

#SPJ1

mcdonald's must communicate an effective message to meet the challenge of itsmultiple choicecompetitors.finances.partners.government.legal requirements.

Answers

McDonald's must communicate an effective message to meet the challenge of its competitors (Option A)

What is advertising?

Advertising is a method of communicating information to customers about products or services through various media, including newspapers, billboards, radio, television, and the internet. In order to achieve its goals, advertising can use a variety of strategies and techniques.

The purpose of advertising is to persuade customers to buy a product or service, and it is a key component of a company's marketing strategy.

A company must communicate an effective message to meet the challenge of its competitors. The primary aim of advertising is to create a positive image of a product or service in the minds of customers. It can be used to increase sales, build brand recognition, and establish a company's reputation.

Advertising is frequently used by businesses as a way of reaching out to customers and getting their message across to them effectively. In conclusion, the answer to the question is competitors.

Learn more about advertising at

https://brainly.com/question/29564877

#SPJ11

a government bond with a coupon rate of 5% makes semiannual coupon payments on january 13 and july 13 of each year. the wall street journal reports the asked price for the bond on january 28 at $1,001.250. what is the invoice price of the bond? the coupon period has 182 days. (round your answer to 2 decimal places.)

Answers

The invoice price of the bond is the price at which the bond is originally issued. In this case, the invoice price of the bond is $1000.00.

To calculate the invoice price, the following formula is used:

Invoice price = (Face value + Coupon payment) / (1 + (Coupon rate / 2))

For this question, the face value of the bond is $1000. The coupon rate is 5%, and the coupon payment is $25. The coupon period has 182 days.

Using the formula above, the invoice price of the bond is:

Invoice price = ($1000 + $25) / (1 + (5% / 2))

Invoice price = $1000.00

Therefore, the invoice price of the bond is $1000.00. This is the original price at which the bond is issued.

When the Wall Street Journal reported the asked price for the bond at $1001.250 on January 28th, it was higher than the invoice price of the bond. This is because the bond was trading at a premium, and thus the asked price was higher than the invoice price.

This difference between the invoice price and the asked price is a result of the coupon period having 182 days. This means that the bond has been in circulation for a longer period of time, and the asked price reflects this by being slightly higher than the invoice price.

In conclusion, the invoice price of the bond is $1000.00. This is the original price at which the bond was issued, and the asked price of $1001.250 on January 28th is a result of the coupon period having 182 days.

To know more about invoice price, refer here:

https://brainly.com/question/27824461#

#SPJ11

which of the following models (developed in 1996) helps to integrate the operations of supply chain members by linking the delivery operations of a seller to the sourcing operations of a buyer? a. gscm b. scor c. dcor d. balanced scorecard

Answers

The Supply Chain Operations Reference (SCOR) model, developed in 1996, helps to integrate the operations of supply chain members by linking the delivery operations of a seller to the sourcing operations of a buyer. Therefore, the correct answer is B: "SCOR".

The Supply Chain Operations Reference (SCOR) model is a process framework used to assess and improve supply chain efficiency and effectiveness. It provides a standard language, metrics, and best practices for managing and measuring supply chain performance across industries and companies.

Therefore, option B: SCOR is the correct answer tot his question.

You can learn more about supply chain at

https://brainly.com/question/25160870

#SPJ11

______ are the firm's level of investments to maintain or build a resource.

Answers

Capital expenditures are the firm's level of investments to maintain or build a resource.

Capital expenditures are investments made by a business to purchase or improve long-term fixed assets, such as property, plant, and equipment (PP&E), which are necessary for its operations, while capital investments refer to investments made in a company's securities by other companies or individuals.

In the accounting sense, capital expenditures (CAPEX) are shown on the balance sheet as assets, such as property, plant, and equipment (PP&E), and are subject to depreciation or amortization over the asset's useful life. When a company buys or enhances its fixed assets, it creates a capital expenditure, which is a long-term investment that will provide future value over a period of time.

In a corporation, these investments are planned in advance and are included in the capital budget, which is a business plan for long-term capital expenditures. Capital expenditure decision-making is based on a company's potential to generate future profits, which are calculated by weighing the investment's initial outlay against the future cash flows generated by it.

Learn more about Capital expenditures here: https://brainly.com/question/29773439

#SPJ11

when there is a sharp decline in the cboe volatility index (vix), stock prices also tend to decline. group of answer choices false true

Answers


The statement that when there is a sharp decline in the CBOE Volatility Index (VIX), stock prices also tend to decline, is true. The CBOE Volatility Index (VIX) is a measure of market volatility and is often referred to as the “fear gauge”, as it is a measure of the expectation of volatility over the next 30 days.

When the VIX is high, it typically indicates that investors are expecting a sharp market move, either up or down. When the VIX is low, it typically indicates that investors are expecting a relatively calm and steady market. Therefore, when the VIX experiences a sharp decline, this is often a sign that investors are becoming more confident and less fearful, and that stock prices will tend to follow suit.

To illustrate this, consider the recent market volatility caused by the coronavirus pandemic. As the virus spread, market uncertainty increased and the VIX spiked to an all-time high of 82.69. This was followed by a sharp decline in the VIX, as investors became increasingly confident that the worst of the crisis was over. This confidence was reflected in the stock market, and the S&P 500 rose by approximately 25%.

Overall, the statement that when there is a sharp decline in the CBOE Volatility Index (VIX), stock prices also tend to decline, is true. The VIX is a measure of market volatility, and when it declines, it typically indicates that investors are becoming more confident and stock prices will rise as a result.

To know more about refer here :

https://brainly.com/question/28518054

#SPJ11

a bond has a par value of $1,000, a current yield of 8.03 percent, and semiannual coupon payments. the bond is quoted at 102.73. what is the coupon rate of the bond?

Answers

A bond has a par value of $1,000, a current yield of 8.03 percent, and semiannual coupon payments. The bond is quoted at 102.73.  The coupon rate of the bond is 4.09%.

What is the coupon rate of the bond?

The coupon rate is the fixed interest rate that is paid semi-annually by the issuer to the bondholders on the par value of the bond. It is given in the bond certificate, and it is a proportion of the nominal value. The coupon rate is required to calculate the coupon payment, which is a fixed payment that the bond issuer pays to the bondholder until the bond reaches maturity.

Solution:

Let us use the formula of the bond which is given as: Bond price = (Coupon payment * (1 - (1 / (1 + r) ^ n))) / r + F / (1 + r) ^ n Where F is the face value, r is the required rate of return, n is the number of years to maturity, and the Coupon payment is the sum of interest payments on the bond, given as: Coupon payment = (Coupon rate * F) / m

Here, F = $1,000 and m = 2 since there are semiannual coupon payments. Then we have:102.73 = (Coupon payment * (1 - (1 / (1 + 0.04015) ^ 20) / 0.04015 + 1,000 / (1 + 0.04015) ^ 20Where r = 8.03% / 2 = 0.04015Substituting for Coupon payment, we get:102.73 = ((Coupon rate * 1,000) / 2 * (1 - (1 / (1 + 0.04015) ^ 20) / 0.04015 + 1,000 / (1 + 0.04015) ^ 20Multiplying both sides by 0.04015, we get:102.73 * 0.04015 = (Coupon rate * 1,000 / 2 * (1 - (1 / (1 + 0.04015) ^ 20))) + 1,000 / (1 + 0.04015) ^ 20

Simplifying, we get:4.133 = (Coupon rate * 1,000 / 2 * (1 - (1 / (1.04015) ^ 20))) + 1,000 / (1.04015) ^ 20Coupon rate * (1 - (1 / (1.04015) ^ 20))) = (4.133 - 1000 / (1.04015) ^ 20) * 2 / 1000Multiplying both sides by 1000 / 2 and simplifying, we get: Coupon rate * (1 - (1 / (1.04015) ^ 20))) = 0.00826604Coupon rate = 0.00826604 / (1 - (1 / (1.04015) ^ 20)

Coupon rate = 4.09% Therefore, the coupon rate of the bond is 4.09%.

To know more about coupon rate refer here :

https://brainly.com/question/16913107#

#SPJ11

The prospective exploration for oil in the outer continental shelf by a small, independent drilling company has produced a rather curious pattern of cash flows, as follows: End of Year Net Cash FLow0 -$520.0001-10 +2000.00010 -1.500.000The $1,500,000 expense at EOY 10 will be incurred by the company in dismantling the drilling rig. a. Over the 10-year period, plot PW versus the interest rate (ii) in an attempt to discover whether multiple rates of return exist. (7 points) b. Based on the projected net cash flows and results in Part (a), what would you recommend regarding the pursuit of this project? Customarily, the company expects to earn at least 20% per year on invested capital before taxes. Use the ERR method ( ϵ=20%). (8 points)

Answers

The given questions regarding interest rate and rates of return can be solved using details of cash flows of the independent drilling company. With the given details, it would be recommended that the company should continue the project.

a. Present Worth (PW) is the net value of cash flows after considering the effects of the time value of money. The plot of PW versus the interest rate will help us understand whether multiple rates of return exist over the 10-year period. To begin with, we calculate the present worth factor (PWF) for each year. The formula for calculating PWF is:

PWF = 1 / (1 + i)n, where, i = interest rate and n = number of years. For example, PWF for the first year is:

PWF1 = 1 / (1 + i)1

Now, we can calculate the present worth (PW) for each year using the formula: PW = Net cash flow × PWF

We will get the following table for PW:

End of Year Net Cash Flow PWF PW

0 -$520,000 1 -$520,0001 $2,000,000 0.909 $1,818,0002 $2,000,000 0.826 $1,652,0003 $2,000,000 0.751 $1,502,0004 $2,000,000 0.683 $1,366,0005 $2,000,000 0.621 $1,242,0006 $2,000,000 0.564 $1,128,0007 $2,000,000 0.513 $1,026,0008 $2,000,000 0.466 $932,0009 $2,000,000 0.424 $848,00010 -$1,500,000 0.386 -$579,000

Expected Rate of Return (ERR) is the minimum required rate of return that the company expects from its investment. In this case, the ERR is 20%. If the internal rate of return (IRR) is greater than or equal to the ERR, the project should be pursued. If the IRR is less than the ERR, the project should be rejected. The formula for calculating IRR is:

PW = 0, where PW is the present worth of cash flows. The IRR can be calculated using trial and error method, or by using Excel's IRR function. Using Excel's IRR function, we get the IRR as 29.9%. Since the IRR is greater than the ERR of 20%, the project should be pursued. Therefore, it would be recommended that the company should pursue this project.

To learn more about cash flows, visit: https://brainly.com/question/10922478

#SPJ11

1. what type of discount would lennox offer its air conditioner dealers if they placed their orders and received delivery before april 1, prior to the normal buying season when air conditioner sales are highest?

Answers

Lennox may offer air conditioner dealers a discount if they place their orders and receive delivery before April 1, prior to the normal buying season when air conditioner sales are highest. Depending on the amount of the order, the discount could range from 5%-10%.

This type of discount encourages dealers to purchase their air conditioners early, helping Lennox to fill their order quotas and generate more sales.

In order to take advantage of the discount, dealers must first place their orders with Lennox and make the payment within a certain time frame. After the order is placed and the payment is made, Lennox will then provide the dealers with a confirmation of the order, along with the discounted price.

Then, the dealers will receive the delivery of the air conditioners on or before April 1. Lennox may also require dealers to sign a contract before the discount is applied.

This type of discount helps Lennox and its dealers by providing an incentive to purchase the air conditioners early. This can help Lennox meet their order quotas, while also giving dealers the opportunity to purchase the air conditioners at a discounted rate. This discount also helps to boost sales during a time when air conditioner sales are usually lower.

To learn more about discount here:

https://brainly.com/question/1548141#

#SPJ11

weston's hardware sells picnic table sets for $498. after marking them up $183 based on selling price, what is the markup percent?

Answers

The markup percent for Weston's Hardware selling picnic table sets for $498 after marking them up $183 is 37%.

To calculate the markup percent, use the following formula: (Markup/Selling Price) x 100 = Markup Percent. In this example, the markup is $183, and the selling price is $498. Plugging in the values gives us (183/498) x 100 = 36.72%, or 37%.

In the context of a business, markup is the difference between the cost of the goods and the selling price. For example, if Weston's Hardware buys the picnic table sets for $315 and then sells them for $498, their markup is $183. This markup is then used to determine the markup percent, which in this example is 37%.

Markup percent is an important metric for businesses, as it provides insight into how much they are making off of each sale. Knowing this metric helps businesses adjust their prices accordingly in order to maximize their profits.

In conclusion, the markup percent for Weston's Hardware selling picnic table sets for $498 after marking them up $183 is 37%.

To learn more about markup percent  here:

https://brainly.com/question/852329#

#SPJ11

in accounting, which of the following payment types is journalized as if it were a cash transaction? question 13 options: eft debit card check all of the above

Answers

All of the above payment types can be journalized as if they were cash transactions.

What is payment?

Payment is the transfer of money from one party to another in exchange for goods, services, or to fulfill a legal obligation. Payment can be made in a variety of forms including cash, online transfers, checks, debit or credit cards, or other financial instruments. Payment is often used to discharge a debt or as consideration for a contract. Payment also refers to the act of making or receiving financial sums in exchange for goods or services. Payment systems are the mechanisms used to facilitate payments, such as credit cards, debit cards, or Pay Pal.

Electronic Funds Transfer (EFT), debit cards, and checks can all be journalized as if they were cash payments. The key difference between these payment types and a cash payment is that the funds are transferred electronically or through a third party, rather than in cash. Therefore, the journal entries to record these payments in the accounting books will be the same as if they were cash payments.

To learn more about payment
https://brainly.com/question/26049409
#SPJ1

Complete Question:
in accounting, which of the following payment types is journalized as if it were a cash transaction? question 13 options:

A) eft,  B) debit card C. all of the above D. non of these

what tasks are firms increasingly using artificial intelligence (ai) to complete? (choose every correct answer.) multiple select question. speech recognition decision making translations psychological counseling

Answers

Artificial intelligence is a branch of computer science that involves the creation of intelligent machines that work and respond like humans. AI has the ability to perform a variety of tasks that were once performed solely by humans. Here are some tasks that firms are increasingly using AI to complete:

Speech recognition: One of the most common applications of AI is speech recognition. Companies are using AI-based voice assistants to answer customer queries, to receive and process orders, to schedule appointments, and to carry out other tasks.

Decision-making: Firms are also using AI to make decisions. AI can analyze vast amounts of data and provide insights that can help managers make better decisions. For example, AI can be used to analyze customer data to identify patterns and trends that can help firms develop new products or services.

Translations: Another area where AI is being used is translations. AI-powered translation software can translate text from one language to another with a high degree of accuracy. This is particularly useful for businesses that operate in multiple countries and need to communicate with customers in different languages.

Psychological counseling: AI is also being used in the field of psychology. Some companies are using AI-based chatbots to provide psychological counseling to patients. These chatbots can analyze the patient's responses and provide appropriate advice and support.

In conclusion, firms are increasingly using AI to complete a variety of tasks. These include speech recognition, decision-making, translations, and psychological counseling.

AI has the ability to perform these tasks with a high degree of accuracy and speed, which makes it an attractive option for businesses looking to improve efficiency and productivity.

To learn more about Artificial intelligence here:

https://brainly.com/question/20339012#

#SPJ11

tom thompson expects to invest $10,000 at 12% and, at the end of a certain period, receive $96,463. how many years will it be before thompson receives the payment?

Answers

Tom Thompson expects to invest $10,000 at 12%. At the end of a certain period, he expects to receive $96,463. To calculate how many years it will take for him to receive the payment, we need to use the formula for compound interest:

A = P (1 + r/n)nt

Where A is the future value of the investment, P is the principal amount, r is the rate of interest, n is the number of times the interest is compounded each year, and t is the number of years the money is invested for.

Plugging in the given values, we get:

$96,463 = $10,000 (1 + 0.12/1)1t

Simplifying, we get:

t = 8.5 years

Therefore, Tom Thompson will receive his payment after 8.5 years.

To know more about investment here

https://brainly.com/question/15353704

#SPJ4

joan has an adjustable-rate mortgage (arm). it has an initial interest rate of 7% adjusted annually with a 2/5 interest rate cap. if interest rates go up, what is the highest interest rate joan could pay in the second year?

Answers

Joan has an adjustable-rate mortgage (ARM).  the highest interest rate Joan could pay in the second year is 9.8%

A mortgage loan with an interest rate that is periodically altered based on an index that reflects the cost to the lender of borrowing on the credit markets is known as a variable-rate mortgage, adjustable-rate mortgage, or tracker mortgage. The base rate or standard variable rate set by the lender may be used for the loan.

The interest rate cap means that the interest rate cannot increase by more than 2/5 (or 0.4) percentage points in any given adjustment period.

If the initial interest rate is 7%, the highest interest rate Joan could pay in the second year would be:

7% + (0.4 x 7%) = 7% + 2.8% = 9.8%

So, the highest interest rate Joan could pay in the second year is 9.8%.

Learn more about adjustable rate mortgage at https://brainly.com/question/14989714

#SPJ11

the label on the workplace container must include abbreviations, formulas, and/or inter-departmental terminologies. a) true b) false

Answers

The statement the label on the workplace container must include abbreviations, formulas, and/or inter-departmental terminologies is false because Pictograms, a signal word, warnings, the name of the product, and the supplier information must all be present on labels.

The dates when the original containers were received and opened should be written on them. This is acceptable laboratory practice for ALL materials, but is especially crucial for substances that can generate peroxide and other unstable substances over time. The product name, hazard pictograms, signal words, hazard statements, precautionary remarks, and supplier contact information can all be found on the supplier label.

To learn more about workplace, click here.

https://brainly.com/question/19965171

#SPJ4

mentoring moment: legal and ethical considerations in pricing sellers should consider legal and ethical issues when setting price. pricing strategies to avoid include those that break the law or put populations at risk of harm. drag each description to the appropriate illegal or unethical strategy. when you have categorized all the items, click submit.

Answers

To ensure that your pricing strategies are both legal and ethical, it is important to familiarize yourself with relevant laws and regulations in your industry and to treat customers fairly and transparently.

How to distinguish them?

In this mentoring moment, let's discuss legal and ethical considerations in pricing. Sellers should always consider legal and ethical issues when setting prices to avoid breaking the law or putting populations at risk of harm. Here are some pricing strategies to avoid, categorized as illegal or unethical:

Illegal Pricing Strategy:
1. Price fixing: This occurs when competitors collude to set the same prices for their products or services, effectively removing competition from the market.


2. Predatory pricing: This involves setting prices so low that it drives competitors out of the market, after which the predatory company raises prices to exploit their new monopoly.


3. Price discrimination: Charging different prices to different customers without any cost-based justification, such as offering discounts only to certain groups of people.

Unethical Pricing Strategies:
1. Surge pricing: This refers to the practice of increasing prices during periods of high demand, like during natural disasters or emergencies, taking advantage of consumers in desperate situations.


2. Deceptive pricing: This involves the use of misleading or false advertising to make customers believe they are getting a better deal than they actually are, such as by promoting a "sale" with inflated original prices.


3. Price gouging: Charging excessively high prices for essential goods or services, exploiting customers who have no other options.

To know more about Pricing Strategy visit:

https://brainly.com/question/15586236

#SPJ11

Externalities The public smoking of cigarettes generates costs to society from second hand smoke, therefore, cigarette PRODUCTION imposes costs on people who do not smoke. Moreover, pelvate consumption of cigarettes can start apartment building and wild fires that also impose costs on non-smokers. Luckily, fire extinguishers can help prevent the spread of fires. Use this information to answer the following ced Shirt the relevant demand or supply curve to demonstrate that the market equilbrium over produces cigarettes relative to the social optimum.

Answers

Therefore, the market equilibrium is likely to overproduce cigarettes relative to the social optimum.Thus, it leads to an inefficient allocation of resources.The relevant demand or supply curve to demonstrate that the market equilibrium overproduces cigarettes relative to the social optimum is the market demand curve.

This curve underrepresents the cost of smoking on non-smokers who are affected by second-hand smoke or the risk of wildfires. As per the statement, "The public smoking of cigarettes generates costs to society from second-hand smoke, therefore, cigarette PRODUCTION imposes costs on people who do not smoke. Moreover, private consumption of cigarettes can start apartment building and wildfires that also impose costs on non-smokers. Luckily, fire extinguishers can help prevent the spread of fires.

"Thus, the externalities (costs on non-smokers) exist in the market of cigarettes. Here, the market demand curve does not represent the total benefit derived from consuming cigarettes because it does not include the benefits to non-smokers from not being exposed to second-hand smoke.On the other hand, the market supply curve does not represent the total cost of producing cigarettes because it does not include the costs to non-smokers from exposure to second-hand smoke or from the risk of wildfires.

Learn more about public smoking here:https://brainly.com/question/3541784

#SPJ11

a cpa has accepted the cfo position at a former audit client. during the next audit engagement, the cpa firm should

Answers

If a CPA has accepted the CFO position at a former audit client, the CPA firm should disqualify themselves from the audit engagement.

Disqualify themselves from the audit engagement if the CPA who previously served as the CFO of the client takes a significant role in the audit engagement. This is because accepting an executive position at a former audit client creates a conflict of interest and may impair the CPA's independence and objectivity in conducting the audit. It is important for CPA firms to maintain independence and objectivity in conducting audit engagements to ensure that financial statements are presented fairly and accurately to stakeholders. Therefore, if there is any doubt about the firm's ability to remain independent and objective in the audit engagement, they should disqualify themselves from the engagement.

Learn more about CPA: https://brainly.com/question/28248650

#SPJ11

currently pays a dividend of $5.0, which is expected to grow indefinitely at 4%. if the current value of fake inc. shares based on the constant-growth dividend discount model is $25.0, what is the required rate of return?

Answers

The required rate of return for Fake Inc. based on the constant-growth dividend discount model is the dividend yield plus the dividend growth rate. In this case, the dividend yield is $5.0 / $25.0 = 0.20, and the dividend growth rate is 4%.

Therefore, the required rate of return is 0.20 + 4.0 = 4.20%. The constant-growth dividend discount model can be expressed as:

P = D / (r - g)

Where:

P = the current value of the stock

D = the current dividend per share

r = the required rate of return

g = the expected growth rate of the dividend

In this case, we know that:

D = $5.0

g = 4%

P = $25.0

Substituting these values into the formula, we get:

$25.0 = $5.0 / (r - 4%)

Solving for r, we get:

r - 4% = $5.0 / $25.0

r - 4% = 0.2

r = 0.2 + 4%

r = 4.2%

Therefore, the required rate of return is 4.2%.

Read more about finance here:https://brainly.com/question/989344

#SPJ11

bramble corp has collected the following data concerning one of its products unit sales price $160 total sales is $18,000 units unit cost $75 to investment when we lead $800,000 the roi percentages is

Answers

The correct option is B, Ming Corp. has collected the following data concerning one of its products. The ROI percentage is 55%.

ROI = Profit / Total Investment * 100

Profit = (18,000 * $160) - (18,000 * $105)

        = $28,80,000 - $18,90,000

        = $9,90,000

ROI = $9,90,000 / $18,00,000 * 100

      = 55%

Return on investment (ROI) or return on charges (ROC) is a ratio among net profits (over a duration) and investment (prices because of an investment of some resources at a factor in time). As a performance measure, ROI is used to evaluate the efficiency of an investment or to evaluate the efficiencies of numerous specific investments. In financial terms, it's miles one manner of pertaining to earnings to capital invested.

The motive of the return on investment (ROI) metric is to measure, consistent with period, costs of go back on money invested in an financial entity in an effort to decide whether or not or not to undertake an funding. It's also used as an indicator to examine unique investments within a portfolio.

To learn more about ROI visit here:

brainly.com/question/30049040

#SPJ4

Complete Question: -

Ming Corp. has collected the following data concerning one of its products:

Unit sales price $160

Total sales 18000 units

Unit cost $105

Total investment $1800000

The ROI percentage is

a. 45%

b. 55%

c. 50%

d. 60%

the percentage of sales method to determine bad debt expense emphasizes the a.income statement. b.journal entries. c.balance sheet. d.general ledger.

Answers

The bad debt expenditure technique based on a proportion of sales puts the focus on the balance sheet.

How is the bad debt expense calculated? Using a percentage of sales?

A company might have reported net credit sales of $50,000 for a given accounting period. They predicted that 5% of their credit sales would be difficult to recoup using the percentage of sales approach.

What purposes does the method based on sales percentage serve?

A forecasting approach called the percentage of sales method uses historical and current sales data to generate financial projections. All sales-related expenses, such as inventory and cost of products, are included in this statistic.

To know more about bad debt expenditure visit:-

https://brainly.com/question/29343346

#SPJ1

A reflective profile acts as a tool to help you identify and understand your strengths, interests, skills, personality, and values.a. trueb. false

Answers

The statement "A reflective profile acts as a tool to help you identify and understand your strengths, interests, skills, personality, and values" is true.

A reflective profile can help you gain a deeper understanding of yourself and your personal attributes. It can also help you understand how these personal attributes may influence your decisions and actions.

What is a reflective profile?A reflective profile is a document that summarizes your thoughts, emotions, and experiences. It's an opportunity to reflect on your life, goals, and achievements, as well as your personal and professional development.A reflective profile aims to assist individuals in recognizing their personality and skill strengths and interests, as well as to comprehend their personality and values.

As a result, it is correct to claim that "A reflective profile acts as a tool to help you identify and understand your strengths, interests, skills, personality, and values."A reflective profile's importance:A reflective profile can assist you in identifying and addressing any limitations in your strengths and skills.

As a result, creating a reflective profile may assist you in gaining a better understanding of your limitations and determining ways to overcome them.A reflective profile can assist you in gaining self-awareness, which is crucial to your personal and professional development. A reflective profile may help you figure out what motivates you and what doesn't, which can aid you in making choices and setting goals that are more suited to you.A reflective profile may be used to support your application for further education or work and give you an edge over other candidates. It can show your capability to reflect, think critically, and learn from your experiences.

Learn more about reflective profile: https://brainly.com/question/26642069

#SPJ11

To qualify as an operation for purposes of determining discontinued operations, which of the following must occur? - A strategic shift is represented that will have a major effect on financial results.
- The operation must have completed a separate tax return in the past 2 years.
- A component of the entity has been sold, disposed of, or is held for sale.
- The operation must have been in business for more than 3 years.

Answers

To qualify as an operation for purposes of determining discontinued operations, a component of the entity must have been sold, disposed of, or is held for sale.

In order for an operation to be considered discontinued and reported as such in a company's financial statements, it must meet certain criteria. According to accounting standards, one of the requirements is that a component of the entity (such as a business unit, segment, or asset group) must have been sold, disposed of, or is held for sale.

This means that the company has made a decision to divest itself of this particular part of its operations, which would result in a significant change to its financial results. The other options listed - a strategic shift, completion of a separate tax return, and being in business for more than 3 years - are not specifically required for an operation to qualify as discontinued.

While they may be relevant in certain situations, the sale or disposal of a component of the entity is the key factor in determining whether an operation meets the discontinued operations criteria.

To know more about discontinued operations, refer here:

https://brainly.com/question/20337091#

#SPJ11

a georgia homeowner obtains a judgment for $25,000 against a real estate agent for damages incurred while represented by that licensee in a transaction. in this circumstance, under what conditions might the homeowner receive compensation from the real estate education, research, and recovery fund?

Answers

Georgia homeowners can receive compensation if the court is convinced that homeowner has used every available legal method, including a writ of possession, to recover the $25,000 damages

If a Georgia homeowner wins a $25,000 judgement against a real estate agent for the harms sustained, the homeowner's eligibility for compensation will depend on a number of factors, including the real estate agent's financial capacity to pay judgement and if homeowner has used every available legal avenue to collect the judgement. The homeowner can recover entire judgement sum without needing to engage in further legal action if the real estate agent has financial means to satisfy the award.

However, the homeowner might need to take legal action to collect judgement if the real estate agent is unable to pay it. By a writ of possession, one legal option to recoup the $25,000 damages is possible. A writ of possession is a legal document that gives one party the right to seize the debtor's assets in order to fulfil a court order. The homeowner might be able to collect the judgement sum if they are successful in getting a writ of possession and are able to confiscate the real estate agent's assets.

Read more about compensation on:

https://brainly.com/question/26178761

#SPJ4

based on what you read in the management in action case, assume that la croix tries to reduce its prices below competitors like pepsico and coca-cola, but targets a narrow market. what type of strategy would this be?

Answers

It would be employing a cost leadership strategy with a focus strategy. If La Croix reduces its prices below challengers like PepsiCo and Coca- Cola but targets a narrow request.

This involves minimizing the costs of product and offering a lower price while still staying profitable. By feeding to a specific request, La Croix can separate itself from its challengers and position itself as the go- to option for budget-conscious consumers. By targeting a narrow request, La Croix can fluently align its marketing and product development strategies to more feed to the specific requirements of the target followership.

The cost leadership strategy with a focus strategy can help La Croix produce a competitive advantage and increase its profitability in the long run.

To learn more about Focus Strategy:

https://brainly.com/question/29434556

#SPJ4

if the price increases from equilibrium at $10 to $20, total surplus for the market will decrease by, in numerals, $ .

Answers

If the price increases from equilibrium at $10 to $20, the total surplus for the market will decrease by, in numerals, $1,500

With everything else remaining the same, an increase in demand will result in a rise in the equilibrium price and an increase in supply. Reduced demand will result in a drop in the equilibrium price and a reduction in supply.

Here, The total surplus for the market will decrease by, in numerals, $ 1,500

Decrease in total surplus = 0.5 * ( 20 - 5) * (300 - 100) = $1,500

A market's overall surplus serves as a gauge of the general well-being of all participants. Combined consumer and producer surplus make up this amount. Consumer surplus is the difference between what consumers are willing to pay and what they actually pay for a good.

Learn more about demand at:

https://brainly.com/question/1245771

#SPJ4

when a firm offers customers a loyalty card for car washes, the firm is employing loyalty segmentation, one of two common types of

Answers

When a firm offers customers a loyalty card for car washes, the firm is employing loyalty segmentation, one of two common types of market segmentation.

What is market segmentation?

Market segmentation is a marketing method that involves breaking down a large target audience into smaller, more manageable groups of customers who have common needs or traits. By segmenting your market, you can provide more tailored goods, services, and marketing communications to each group.

This can aid in improving the effectiveness of the marketing campaigns, increasing client satisfaction, and boosting sales. There are two basic types of market segmentation: 1. Customer segmentation 2. Product segmentation

Loyalty segmentation is one of the most widely used customer segmentation techniques. The goal of this method is to identify the most dedicated and valuable customers and offer them rewards or incentives to keep them coming back. Customer loyalty programs are an example of this type of segmentation.

These programs can take a variety of forms, from discounts to free gifts to exclusive access to new products or services.

Learn more about Market segmentation here:

brainly.com/question/15357678

#SPJ11

Other Questions
plants and animals need a variety of resources to carry out and maintain life processes; the most important of these resources is . the phone calls to a computer software help desk occur at a rate of 3 per minute in the afternoon. compute the probability that the number of calls between 2:00 pm and 2:10 pm is: question 5 what are some key benefits of using external data? select all that apply. 1 point external data has broad reach. external data is always reliable. external data can provide industry-level perspectives. external data is free to use. Choose the statements that describe characteristics of a probability distribution? Select all that apply. A. Half of the possible outcomes have associated probabilities grater than 0. 5. B. The probability of an outcome is between 0 and 1. C. The sum of the probabilities of all possible outcomes is 1. D. The distribution is symmetrical. E. The outcomes are mutually exclusive g assume a firm generates $2,209 in sales and has a $326 increase in accounts receivable during an accounting period. based solely on this information, cash flow will increase by (enter your response as a whole number with no decimal places.) How many moles are there in 12.7 g of CaF2? yolanda was born with a rare genetic disease in which the proximal tubules of her nephrons express half the number of aquaporins as is typical. what will be the result? an irrigation system waters a circular field that has a 30-foot radius. find the exact area watered by the irrigation system . the second accent color typically is used to fill color in prominent publications shapes. true false HELPPPPP MEEEEEE!!! PLEASEEEEE 1. Factor: 2x^2 + 9x + 18 What multiples to get 18 and adds to get 9? a. (X+9) (x+2) b. (X+6) (x+3) c. (X-6) (x-3) d. (X-9) (x-2) 2.Factor:X^2 - 20x + 36 What multiples to get 36 and adds to get -20? a. (x-6) (x-6) b. (x+3) (x+12)c. (x-9) (x-4) d. (x-18) (x-2) 3. factor: 2x^2 - 5x -3STEPS. STEP 1* - Slide and Multiply the First Number to the LastSTEP 2 - Factor - What Multiplies to get the Last Number and Adds to get theMiddle Number?STEP 3 - Divide and Reduce - The number we divide by is the same number we slid.STEP 4 - Bottoms Up - If a fraction remains, move bottom number in front of thevariable.*Unless there is a GCF. If there is, pull that out first.a. (x-3)(x+1)b. (2x+1)(x-3) c. (2x-1)(x+3) d. (x-3)(2x-3) 4. what is the greatest common factor? 8x^2 + 18x + 4 a. 2 b. 4 c. 2x d. 4x 5.factor:8x^2 + 18x + 4 STEPS. STEP 1* - Slide and Multiply the First Number to the LastSTEP 2 - Factor - What Multiplies to get the Last Number and Adds to get theMiddle Number?STEP 3 - Divide and Reduce - The number we divide by is the same number we slid.STEP 4 - Bottoms Up - If a fraction remains, move bottom number in front of thevariable.*Unless there is a GCF. If there is, pull that out first.a. (x-2)(4x+1) b. 2(x-2)(4x-1) c. 2(x+2) (4x+1)d. (x+2)(x+4) the strongest intermolecular forces are nearly as strong as the forces that hold atoms together in a molecule. true false michelle just wants to pick out new clothes at target while she shops for supplies for the new school year. yet, because all of her friends shop at urban outfitters, michelle does as well. michelle's behavior is an example of? if the power connector from the cpu fan has only three pins, it can still connect to the 4-pin header, but what functionality is lost? The training effect in muscles starts when a training overload signals genetic changes that eventually produce the appropriate protein. True/False. What did Jemma and her friends do after a hurricane hit their community? (2 points) a Babysat younger children b Went to school for longer hours c volunteered their time to clean up d Watched their parents clean the streets How to make my sentence sound stronger and more advanced? Part 4- The Punic Wars1. What was the cause of the first PunicWar? University/College Research Projectpresentation on a college or university of your choosing. Include Visual Elements - graphic of name of college, graphic of logo, graphic of mascot, 1-2 photos of the campus. Use school colors in creating thebanner.Basic Information -a. Location: city, state.b. Type of school: Public vs private, UC vs Cal state, specialcollege?c. Student body: # of students, % of male/female, % of differentethnicitiesd. Cost: tuition (sem vs gt), fees, room & board, food, othere.costs. Calculate per year.Contact information: address, phone number, email, website.1. Top 6 sports programs (3 male and 3 female) Top 5 clubs /programsh. What is unique or special about this college?For Admission -1. Minimum high school course requirementsj. Minimum GPAk. Minimum SAT /ACT scores1. # of applications submitted each year, # of applications accepted, % acceptedm. Financial Aid: types offered, such as scholarships, grants, loans, etc.College Life -1. What is the history of the school? What traditions do they have?o. Top 10 majors which type of systems testing includes having the customer test the system in an operational setting to see if it is useful? 100 Points!!! Algebra question, only looking for answer to last two. Graph each system of equations and describe it as consistent and independent, consistent and dependent, or inconsistent. Photo attached. Thank you!